Invitation to Bid on Demolition and Replacement of Curbs

The City of Bromley, Kentucky
226 Boone Street
Bromley, Kentucky 41016

Is now accepting sealed bids to be opened at the November 7, 2018 regular council meeting (6:00 p. M.) For the following: Pike and hayward street project improvements.

Demolition and replacement of approximately 190’ of curb on the south side of pike street starting at the intersection of rohman street heading west on pike street to short street. New curb installation approximately 90’ from short street intersection heading west on the south side of pike street.

New curb installation approximately 330’ from rohman street intersection heading west on the north side of pike street. New curb installation approximately 36’ from hayward alley heading west on the south side of pike street to a catch basin.

Demolition of east end entrance section of hayward street and install a new entrance section with a wide apron from roadway for large trucks entering the street.

Specifications for Concrete Work:

Curbs: The new curbs will be 6” high x 6” wide and approximately 18” below grade. Excavate to a depth of 18” approximately. Install gravel base material then form and pour 4,000 psi ae concrete, strip forms and face street side of curb. Sawcut control joints at approximately 10’ on center. Backfill curb with topsoil then seed and straw.

Street entrance: Demolition and disposal of all concrete and soil in excavation areas. Install a tapered 14’ x 31’ section with compacted gravel base material. Form and pour 4,000 psi ae concrete 8” thick for apron with a commercial broom finish and sawcut control joints.

Payment draws: Will be 50% upon commencement of project and 50% upon completed work and signed off by a city official. Winning contractor must provide proof of insurance and be approved by the city before starting any work.